Access Ramp Under Construction for West Entrance to Nave

Having received a $12,000 grant from United Thank Offering, Trinity Church is laying plans for the construction of an access ramp for the West Entrance to its nave.

The Property Committee recommended to hire Larson & Danielson for the destruction of the planter and the construction of the ramp. The Vestry approved this recommendation at the Vestry meeting held on 10/29/07. Construction is due to begin soon.

In related news, the Barker Welfare Foundation has just notified us that it has approved a $15,000 grant to Trinity Church for the purchase of a stair lift for Barker Hall. Dawn Tyler has placed an order for the unit, which should be installed around the end of Nov/early December. It will take 2~3 weeks to custom build the unit to our measurements, and 1 day to install.

Event Anticipated Completion Date
Final drawings from the architect July 2007
Bid requests sent out July 2007
Contractor bids received August 2007
Trinity Church Property Committee reviews bids, award winning contractor with the job August-October 2007
Ramp work begins November 2007
Ramp complete January 2007

Here's the Plan. . .

West Nave Access Ramp

Here's How the Space Looks Now (August, 2007)


Zooming in on the West Side:
Wide View of Church's West Facade
Middle View of Church's West Facade
Close View of Church's West Facade
Close up of Crucifix

Rounding the Corner:

Southwest Corner of Church
West View of Church's Southwest Corner
Close View of Church's Southwest Corner

Work In Progress. . .

Late November, 2007

Deposition of the Cross
Excavations for the Ramp

Setting the forms
Setting the forms
Pouring the Footings

And just in time, too!

Ramp Progress
Ramp Progress
Ramp Progress